WORK COMPLETED:
- Level 4 exterior walls framed
- PMT grounding completed
- Window testing completed
UPCOMING WORK:
- Truss delivery November 12th
- Exterior wall membrane continues
- Window prep continues
- Cladding mock up
Progress photos attached.
Paul Krzywicki
Senior Project Manager